Follow the three ‘GeeZE’ rules for taking repeatable, reliable static readings.

Static sparks are bad. Sparks can shock operators and damage thin coatings such as release layers. Sparks that are too small to see, hear, or feel can ignite flammable solvent vapors. And, sparks deposit spots of static charge on webs that can cause sticking and jamming of cut sheets. Often, our main goal for static control is to suppress sparks.

Static sparks occur when static levels are too high. Keep static low to suppress sparks. While this sounds simple, static is not simple. How much is too much? What level is low enough? To know, we must measure static using a static meter.

A handheld static meter is an electrostatic fieldmeter. Even a device that displays static in ‘KV’ or ‘kilovolts’ responds to the electric field at the meter’s sensor. To take repeatable, reliable static readings, follow these three simple “GeeZE” rules. GeeZE rhymes with cheese.

  • G - Ground the static meter.
  • Z - Zero the static meter.
  • E - Empty the "measurement sphere."

To understand these rules, let’s first look at how a fieldmeter works. In the simple, “parallel plate” model for our static meter in Figure 1, the voltage V on the upper plate represents the static that we want to measure. Our static meter is the grounded, lower plate located distance G below the upper plate. The electric field E “connects” the static that we want to measure with the meter. Our meter reads the electric field, which, when the plates are much bigger than gap G, is the voltage V divided by the gap G. The electric field E has units of volts per distance.

 

Figure 1. Electric field E depends on voltage V and distance D.

 

Even though the display on most static meters says “KV,” the units of the electric field are “KV per distance.” Most handheld fieldmeters are calibrated for a one inch gap, so the electric field is displayed in kilovolts per in. (KV/in). Some meters are calibrated for other gaps, so read the instructions. For example, the Meech 983v2 Static Locator is calibrated for a 150 mm gap. The common, industry standard for acceptably low static, 5 KV/in., would read 30 KV on this meter. The units for the electric field on the Meech meter are really KV per 150 mm, and 150 mm is about 6 in.

In my experience, sparks occur when the electric field is bigger than 15 KV/in. So, when the field exceeds 15 KV/in., improve static control with the goal of keeping static below 5 KV/in. Now that we’ve looked at how a fieldmeter works, the three GeeZE rules are sensible.

 

RULE 1

Ground the static meter. If the lower plate in Figure 1 is ungrounded, its voltage is probably not zero. In fact, the voltage of the meter can be pretty much anything up to about 30 KV, depending on how much charge is on the person holding the meter. Static readings can be highly variable because the static on the web is variable. To take repeatable readings, we must eliminate all other sources of variability. Static readings are highly variable anyway. We must not add more variability.

I wear static dissipative shoes when I take static measurements so that I am grounded, at least when the floor is conductive or static dissipative. Even so, I have a habit of touching the grounded machine frame with one hand while I take the static reading with my other hand. I recommend that you also develop this habit. Touch the machine frame when you take a static reading. The human body is mostly salt water, which is conducting. So, touching the machine frame grounds your body.

 

RULE 2

Zero the static meter. The reading on a fieldmeter drifts with time and temperature. Nearly every sensitive electronic instrument drifts with time and temperature. So, your fieldmeter is designed to be zeroed so that the readings are repeatable. The best way to zero the static meter in Figure 2 is to measure the static on a grounded metal object like building steel, a metal conduit, or the machine frame.

 

Figure 2. Zero your meter when measuring grounded metal.

 

Of course, the static on grounded metal is zero. So, we know that the meter should read zero. Hold the meter at the proper gap G and press the “zero button” or adjust the display to read zero.

Now, we’re ready to take a static reading.

 

RULE 3

Empty the measurement sphere. Well, what is a “measurement sphere?” Fieldmeters display the electric field at the meter’s sensor. While the field E in our parallel plate model in Figure 1 is simple, most of the time, the shape and the size of the electric field is more complex. The field has a different shape and size for each different measurement geometry. Any nearby conducting object will reduce the static reading. Take a static reading at a location where all other conducting objects are far away so that the meter responds only the static on the web. Your static meter is calibrated to read accurately when the meter responds only to the charge on the web.

To ensure that the meter responds only to the static on the web, imagine that you can draw a dot in Figure 3 on the web just below the fieldmeter. The dot is distance G from the meter. Your dot becomes the center of a sphere that, in your mind’s eye, expands out to a radius of 2G. This is the “measurement sphere.” For reliable readings, the measurement sphere in Figure 3 must be empty, well, except for the meter and your hand. For a meter calibrated for a gap G of 1 in., the measurement sphere has a diameter of 4 in., which is just a little bit bigger than a large softball. So, to take a reliable static reading, you’ll need to find an open space on the machine about the size of a softball.

 

Figure 3. The measurement sphere radius 2G must be empty.

 

If you use a meter calibrated for a 150-mm gap, the measurement sphere has a diameter of 600 mm, which is about the size of a large, 2-ft diameter beach ball. Any conducting object inside the beach ball reduces the reading. For this reason, I prefer using a meter calibrated for a smaller gap. I use a Monroe 257D Electrostatic Fieldmeter calibrated for a 1-cm gap. For my meter, the measurement sphere has a diameter of about 1.5 in., which is about the size of a ping pong ball.

Static readings are important for diagnosing static problems and for verifying static control. Follow the three GeeZE rules to make repeatable, reliable static readings:

  1. Ground the meter.
  2. Zero the meter.
  3. Empty the measurement sphere.

I invite you to ask questions about this column and to suggest future topics. My email address is: This email address is being protected from spambots. You need JavaScript enabled to view it..

Static control expert Dr. Kelly Robinson, president of Electrostatic Answers, has 27+ years of experience in problem-solving and consulting. Kelly writes PFFC's Static Beat column and the Kelly on Static blog. Contact him at 585-425-8158; This email address is being protected from spambots. You need JavaScript enabled to view it.; www.electrostaticanswers.com.

 